Miramar Bridge Hwy 1 Detour CalTrans Final Striping 1-Day Work

October 5th, 2020 @ 9:00am - 3:00pm

Mario Andreini of Andreini construction says this will be the last closure for this project.


Miramar Bridge Hwy 1 Detour Construction Begins Friday 9/18/2020

HOT OFF THE “PRESS”!  And fresh from the Starbucks parking lot with Mario Andreini of Andreini Construction. They are the contractor for the Miramar Drive to Medio Drive detour for the Miramar Bridge.

Stay tuned for on-site updates from Mario on Coastside Buzz😊🐝

 

Here is the construction schedule:

Friday 9/18/2020 9:00am to 3:00pm CLOSED

CLOSED: Re-painting the lanes.

Sat and Sun 9/19-9/20/2020 “Open”

OPEN: As in two-way bicycle/pedestrian traffic, unprotected by Hwy 1 traffic. Northbound is head on.  Wait for a break in bike and pedestrian traffic at this point; One way at a time.

Mon thru Fri 9/21/2020 to 9/25/2020; 9:00am to 3:00pm CLOSED

CLOSED: Heavy machinery like trucks and a crane will deliver and install K-Rail.

Miramar Dr and Hwy 1

Cal Trans graffiti translates to back to Coastal Trail this-a-way.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Draft maps provided by San Mateo County Public Works Department (DPW)

 

Draft maps provided by San Mateo County Public Works Department (DPW)