PG&E Utility Relocation Project at Hwy 1 and Silver Ave. ~ First Step for the City of HMB’s Highway 1 North Safety and Operational Improvements Project

July 25th, 2022 @ 10:00pm - August 31st, 2022 @ 5:00am

Beginning Monday, July 25, 2022, PG&E will begin work on the Highway 1 Utility Relocation Project. As a first step in the City’s Highway 1 North Safety and Operational Improvements Project, PG&E will be relocating gas lines on Highway 1 at Silver Avenue.
To accommodate this night work, the northbound lanes will be shifted west onto the median to allow for the relocation of the gas lines to the east.

Informational message boards have been put in place notifying the public of the work.

The project is anticipated to continue through late August (schedule subject to change due to unforeseen circumstances). Hours of work will be 10:00 p.m. to 5:00 a.m.

For any questions or concerns regarding the project you can contact PG&E Public Relations Manager Caitlin Manhold at (650) 582-8301.

Hwy 1 Safety and Operational Improvements – North

Project Description: Operational and safety improvements to Highway 1 between North Main Street and Spindrift Way. Improvements include a Class I multi-use path (10-ft wide with two foot shoulders) from Main St to Spindrift Way on the East side of Highway 1, a new signalized intersection at Terrace Ave, four protected pedestrian crossings, local street connection to Frontage Rd/Terrace intersection, and improvements to bus stop pull-out areas.

Project Status:   Environmental clearance has been certified.  Coastal Development Permit has been issued.  100% design completed and submitted to Caltrans. Utility relocation/protection is being coordinated.

Funding Source(s): Measure A grant from San Mateo County Transportation Authority (SMCTA) and Pacific Ridge Subdivision Traffic Impact Fees.

Latest Update:  (3/15/2022)      100% design has been completed and submitted to Caltrans for their review and approval. Caltrans has been reviewing the latest revisions for final encroachment permit.  Utility relocations for gas line and electric poles are in design.   Right of way certification and utility relocations are expected by the end of 2022.   Regulatory permits to be obtained by 10/1/2022.  Agreement with SMCTA for construction funding to be executed in Summer 2022.  Construction is expected to start in 2023 and last approximately 18 months.

Contact: Ray Razavi, Transportation Engineer, E-mail

More Information:

HMB North Frontage Road South

Details

Start:
July 25th, 2022 @ 10:00pm
End:
August 31st, 2022 @ 5:00am
Event Category:
Website:
https://www.facebook.com/cityofhalfmoonbay

Venue

Silver Ave. Half Moon Bay
Silver Ave.
Half Moon Bay, CA 94019 United States
+ Google Map